Red-Rochester project forges ahead - making plans and scheduling for the arrival of new boilers at The Park

Red-Rochester project forges ahead - making plans and scheduling for the arrival of new boilers at The Park

RED-Rochester has been working closely with EBP site operations, ESI (our CM), numerous sub-contractors, the boiler vendors, and their transport haulers and the project equipment erectors to arrive at a plan to minimize any disruptions to EBP activities and still allow the boilers to be delivered. Key to this happening smoothly is two-way communication between the RED-Rochester project team and the different operations within the EBP.   The new boilers are being fabricated in Abilene, Texas (#45) and Tulsa, Oklahoma (# 46-48). Tentative delivery dates are currently set for later in April…  read more →

Posted in: Eastman Business Park  |  Tagged: EBP gas conversion project, RED-Rochester